Thanks for the question.
If briefly - we've participated in the project regarding implementation of internal TMS in our headquarter. This system was already developed on Ax 3.0 and had web-interface (on EP). Implementation of this system took approx 3,5 thousands of hours.
What we've had to do are:
1. Transfer application from 3.0 till 4.0
2. Apply the new best practice
3. Setup SharePoint portal for Web access
I suppose you can imagine that it wasn't an easy walk to perform these activities. But it was really interesting to work with the new system (when the project kicked off - there was only 1st drop of Ax).
This project continued from Dec'05 till May'06 and at the moment we provide support of the system.
Hope this brief answer is quite satisfying
If you have any additional questions, feel free to contact with me by e-mail.
Sincerely,